Anduril’s Sydney facility has successfully completed the assembly of the first Ghost Shark vehicle, arriving notably ahead of the projected timeline. This achievement not only underscores the efficiency of the newly inaugurated factory but also sets a precedent for accelerated production cycles in undersea defense technology. The Ghost Shark vehicle, engineered for stealth and resilience in deep-water environments, is now poised to enter a rigorous phase of acceptance testing, marking a critical step toward operational deployment.

The cutting-edge assembly line incorporated several key innovations that contributed to early completion:

  • Advanced modular components enabling rapid integration
  • AI-driven quality assurance protocols to minimize rework
  • Collaborative robotic systems streamlining assembly tasks
Milestone Scheduled Date Actual Completion Impact
Factory Commissioning March 2024 March 2024 On schedule
First Vehicle Assembly Start April 10, 2024 April 8, 2024 2 days early
Assembly Completion May 25, 2024 May 20, 2024 5 days early